Georgia Power IC-958 (IC-958)

Georgia Power IC-958 is a 2,131.0 MW gas interconnection project in Cobb County, Georgia with a current status of withdrawn. It is proposed to connect at Jack McDonough Substation 230 kV Bus.

2,131.0 MWCapacity
WithdrawnStatus
GAMarket
GasTechnology

Project facts

Canonical nameGeorgia Power IC-958
Queue IDIC-958
Statuswithdrawn
Source status
MarketGA
TechnologyGas
Capacity2,131.0 MW
StateGeorgia
CountyCobb County
Point of interconnectionJack McDonough Substation 230 kV Bus
Requested (queue) date2021-05-13
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Power

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: soco-oatt-queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata