Gibson Sta - Bedford 345 345.0kV (J4063)

Gibson Sta - Bedford 345 345.0kV is a 300.0 MW wind interconnection project in Knox, Indiana with a current status of operational. It is proposed to connect at Gibson Sta - Bedford 345 345.0kV.

300.0 MWCapacity
OperationalStatus
Market
WindTechnology

Project facts

Canonical nameGibson Sta - Bedford 345 345.0kV
Queue IDJ4063
Statusoperational
Source statusActive
Market
TechnologyWind
Capacity300.0 MW
StateIndiana
CountyKnox
Point of interconnectionGibson Sta - Bedford 345 345.0kV
Requested (queue) date2025-09-04
Proposed in-service date2030-08-01
Operational date2030-08-01
Withdrawn date
Developer
Utility / transmission ownerDuke Energy Progress

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata