GNA Energy (G57)

GNA Energy is a 105.0 MW wind interconnection project in Sherman, Oregon with a current status of withdrawn. It is proposed to connect at Big Eddy-DeMoss 115 kV line.

105.0 MWCapacity
WithdrawnStatus
ORMarket
WindTechnology

Project facts

Canonical nameGNA Energy
Queue IDG57
Statuswithdrawn
Source statusWITHDRAWN
MarketOR
TechnologyWind
Capacity105.0 MW
StateOregon
CountySherman
Point of interconnectionBig Eddy-DeMoss 115 kV line
Requested (queue) date2001-05-22
Proposed in-service date2003-09-01
Operational date
Withdrawn date
DeveloperSeawest Windpower, Inc.
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata