GPlains Storage (28INR0228)

GPlains Storage is a 51.3 MW other interconnection project in Ector, Texas with a current status of operational. It is proposed to connect at Tap 138kV WOLFSS_8 (1013) - SANDHLTA_8 (1103) .

51.3 MWCapacity
OperationalStatus
EctorMarket
OtherTechnology

Project facts

Canonical nameGPlains Storage
Queue ID28INR0228
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEctor
TechnologyOther
Capacity51.3 MW
StateTexas
CountyEctor
Point of interconnectionTap 138kV WOLFSS_8 (1013) - SANDHLTA_8 (1103)
Requested (queue) date2025-04-21
Proposed in-service date
Operational date2029-06-21
Withdrawn date
DeveloperGypsum Plains Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.