Grape (63851_GRAPE)

Grape is a 246.4 MW solar interconnection project in Kings, California with a current status of active.

246.4 MWCapacity
ActiveStatus
CISOMarket
SolarTechnology

Project facts

Canonical nameGrape
Queue ID63851_GRAPE
Statusactive
Source status(T) Regulatory approvals received. Not under construction
MarketCISO
TechnologySolar
Capacity246.4 MW
StateCalifornia
CountyKings
Point of interconnection
Requested (queue) date
Proposed in-service date2027-03-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerWestlands Grape, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.