Grasshopper Solar (24INR0125)

Grasshopper Solar is a 407.7 MW solar interconnection project in Haskell, Texas with a current status of operational. It is proposed to connect at Smoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637.

407.7 MWCapacity
OperationalStatus
HaskellMarket
SolarTechnology

Project facts

Canonical nameGrasshopper Solar
Queue ID24INR0125
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketHaskell
TechnologySolar
Capacity407.7 MW
StateTexas
CountyHaskell
Point of interconnectionSmoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637
Requested (queue) date2021-09-28
Proposed in-service date
Operational date2028-10-01
Withdrawn date
DeveloperGrasshopper Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.