Grassy Falls (O45)

Grassy Falls is a 143.0 MW other interconnection project in Greenbrier, West Virginia with a current status of withdrawn.

143.0 MWCapacity
WithdrawnStatus
—Market
OtherTechnology

Project facts

Canonical nameGrassy Falls
Queue IDO45
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyOther
Capacity143.0 MW
StateWest Virginia
CountyGreenbrier
Point of interconnection—
Requested (queue) date2005-07-21
Proposed in-service date2007-11-01
Operational date—
Withdrawn date2009-01-06
Developer—
Utility / transmission ownerAPS

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.