Gravel Neck is a 91.9 MW gas interconnection project in Surry, Virginia with a current status of operational.

91.9 MWCapacity
OperationalStatus
PJMMarket
GasTechnology

Project facts

Canonical nameGravel Neck
Queue ID7032_3
Statusoperational
Source status(OP) Operating
MarketPJM
TechnologyGas
Capacity91.9 MW
StateVirginia
CountySurry
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date1989-10-01
Withdrawn date—
Developer—
Utility / transmission ownerVirginia Electric & Power Co

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata