Green County-Marion County 161 kV (AG1-353 - moved to TC1)

Green County-Marion County 161 kV is a 98.0 MW solar interconnection project in Taylor, Kentucky with a current status of withdrawn.

98.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameGreen County-Marion County 161 kV
Queue IDAG1-353 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity98.0 MW
StateKentucky
CountyTaylor
Point of interconnection—
Requested (queue) date2020-09-30
Proposed in-service date2023-12-31
Operational date—
Withdrawn date2025-01-22
Developer—
Utility / transmission ownerEKPC

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata