Hackberry Creek Solar is a 175.5 MW solar interconnection project in Mitchell, Texas with a current status of operational. It is proposed to connect at tap 345kV 10053 Cattleman Switch - 1058 Longshore Switch .
175.5 MWCapacity
OperationalStatus
MitchellMarket
SolarTechnology
Project facts
| Canonical name | Hackberry Creek Solar |
|---|---|
| Queue ID | 25INR0430 |
| Status | operational |
| Source status | SS Completed, FIS Completed, IA |
| Market | Mitchell |
| Technology | Solar |
| Capacity | 175.5 MW |
| State | Texas |
| County | Mitchell |
| Point of interconnection | tap 345kV 10053 Cattleman Switch - 1058 Longshore Switch |
| Requested (queue) date | 2023-07-31 |
| Proposed in-service date | — |
| Operational date | 2028-07-01 |
| Withdrawn date | — |
| Developer | Hackberry Creek Solar LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata