Halfway 12.5kV (X2-038)

Halfway 12.5kV is a 2.0 MW gas interconnection project in Washington, Maryland with a current status of withdrawn.

2.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameHalfway 12.5kV
Queue IDX2-038
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity2.0 MW
StateMaryland
CountyWashington
Point of interconnection
Requested (queue) date2011-06-10
Proposed in-service date2013-10-31
Operational date
Withdrawn date2016-01-14
Developer
Utility / transmission ownerAPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.