HARMONY STORAGE 2 (1892)

HARMONY STORAGE 2 is a 300.0 MW battery interconnection project in Contra Costa, California with a current status of active. It is proposed to connect at Contra Costa PP 230 kV .

300.0 MWCapacity
ActiveStatus
GBAMarket
BatteryTechnology

Project facts

Canonical nameHARMONY STORAGE 2
Queue ID1892
Statusactive
Source statusACTIVE
MarketGBA
TechnologyBattery
Capacity300.0 MW
StateCalifornia
CountyContra Costa
Point of interconnectionContra Costa PP 230 kV
Requested (queue) date2021-04-15
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata