Harrisburg Substation 115 kV-12.47 kV (L0587)

Harrisburg Substation 115 kV-12.47 kV is a 14.0 MW other interconnection project in Linn, Oregon with a current status of active. It is proposed to connect at BPA's Harrisburg Substation.

14.0 MWCapacity
ActiveStatus
ORMarket
OtherTechnology

Project facts

Canonical nameHarrisburg Substation 115 kV-12.47 kV
Queue IDL0587
Statusactive
Source statusCONST AGRMT EXE
MarketOR
TechnologyOther
Capacity14.0 MW
StateOregon
CountyLinn
Point of interconnectionBPA's Harrisburg Substation
Requested (queue) date2023-12-04
Proposed in-service date2026-12-05
Operational date
Withdrawn date
DeveloperConsumers Power, Inc.
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata