Hayhurst Texas Solar (22INR0363)

Hayhurst Texas Solar is a 24.8 MW solar interconnection project in Culberson, Texas with a current status of operational. It is proposed to connect at tap 138 kV Three Mile Draw Switch – Horseshoe Springs Switch Line .

24.8 MWCapacity
OperationalStatus
CulbersonMarket
SolarTechnology

Project facts

Canonical nameHayhurst Texas Solar
Queue ID22INR0363
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketCulberson
TechnologySolar
Capacity24.8 MW
StateTexas
CountyCulberson
Point of interconnectiontap 138 kV Three Mile Draw Switch – Horseshoe Springs Switch Line
Requested (queue) date2020-08-21
Proposed in-service date
Operational date2025-11-28
Withdrawn date
DeveloperHayhurst Texas Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata