Hazel Creek 230 kV Substation (J1149)

Hazel Creek 230 kV Substation is a 200.0 MW solar interconnection project in Yellow Medicine County, Minnesota with a current status of withdrawn. It is proposed to connect at Hazel Creek 230 kV Substation.

200.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameHazel Creek 230 kV Substation
Queue IDJ1149
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity200.0 MW
StateMinnesota
CountyYellow Medicine County
Point of interconnectionHazel Creek 230 kV Substation
Requested (queue) date2018-03-12
Proposed in-service date2021-11-15
Operational date2021-11-15
Withdrawn date2020-03-25
Developer
Utility / transmission ownerNORTHERN STATES POWER COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.