HAZEL CREEK (J2550)

HAZEL CREEK is a 75.0 MW battery interconnection project in Yellow Medicine, Minnesota with a current status of operational. It is proposed to connect at HAZEL CREEK.

75.0 MWCapacity
OperationalStatus
Market
BatteryTechnology

Project facts

Canonical nameHAZEL CREEK
Queue IDJ2550
Statusoperational
Source statusActive
Market
TechnologyBattery
Capacity75.0 MW
StateMinnesota
CountyYellow Medicine
Point of interconnectionHAZEL CREEK
Requested (queue) date2022-09-14
Proposed in-service date2030-07-18
Operational date2030-07-18
Withdrawn date
Developer
Utility / transmission ownerNORTHERN STATES POWER COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata