High Sheldon Windfarm (0144)

High Sheldon Windfarm is a 112.5 MW wind interconnection project in Wyoming, New York with a current status of operational. It is proposed to connect at Stolle Rd-Meyer 230kV.

112.5 MWCapacity
OperationalStatus
CMarket
WindTechnology

Project facts

Canonical nameHigh Sheldon Windfarm
Queue ID0144
Statusoperational
Source status14
MarketC
TechnologyWind
Capacity112.5 MW
StateNew York
CountyWyoming
Point of interconnectionStolle Rd-Meyer 230kV
Requested (queue) date2004-02-18
Proposed in-service date
Operational date
Withdrawn date
DeveloperSheldon Energy, LLC
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.