Hillsboro-Wildcat 138kV (AC1-089)

Hillsboro-Wildcat 138kV is a 150.0 MW solar interconnection project in Highland, Ohio with a current status of operational.

150.0 MWCapacity
OperationalStatus
—Market
SolarTechnology

Project facts

Canonical nameHillsboro-Wildcat 138kV
Queue IDAC1-089
Statusoperational
Source statusIn Service
Market—
TechnologySolar
Capacity150.0 MW
StateOhio
CountyHighland
Point of interconnection—
Requested (queue) date2016-10-15
Proposed in-service date—
Operational date2024-01-19
Withdrawn date—
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.