Hitchland - Moore 230kV line (GEN-2024-045)

Hitchland - Moore 230kV line is a 345.0 MW solar interconnection project in Hansford, Texas with a current status of withdrawn. It is proposed to connect at Hitchland - Moore 230kV line.

345.0 MWCapacity
WithdrawnStatus
TXMarket
SolarTechnology

Project facts

Canonical nameHitchland - Moore 230kV line
Queue IDGEN-2024-045
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologySolar
Capacity345.0 MW
StateTexas
CountyHansford
Point of interconnectionHitchland - Moore 230kV line
Requested (queue) date2024-10-30
Proposed in-service date2029-12-01
Operational date
Withdrawn date2026-05-21
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.