Homer City-Mainesburg 345kV is a 989.0 MW gas interconnection project in Clearfield, Pennsylvania with a current status of withdrawn.

989.0 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameHomer City-Mainesburg 345kV
Queue IDAB1-175
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyGas
Capacity989.0 MW
StatePennsylvania
CountyClearfield
Point of interconnection—
Requested (queue) date2015-10-30
Proposed in-service date2020-01-01
Operational date—
Withdrawn date2015-11-19
Developer—
Utility / transmission ownerPENELEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.