Homer City-Wayne 345kV (B43)

Homer City-Wayne 345kV is a 284.0 MW gas interconnection project in Venango, Pennsylvania with a current status of withdrawn.

284.0 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameHomer City-Wayne 345kV
Queue IDB43
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyGas
Capacity284.0 MW
StatePennsylvania
CountyVenango
Point of interconnection—
Requested (queue) date1999-11-29
Proposed in-service date—
Operational date—
Withdrawn date2000-11-08
Developer—
Utility / transmission ownerPENELEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata