Honda Marysville Tap 69 kV (AH1-483)

Honda Marysville Tap 69 kV is a 42.0 MW battery interconnection project in Union, Ohio with a current status of withdrawn.

42.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameHonda Marysville Tap 69 kV
Queue IDAH1-483
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity42.0 MW
StateOhio
CountyUnion
Point of interconnection—
Requested (queue) date2021-09-10
Proposed in-service date2024-09-23
Operational date—
Withdrawn date2024-12-18
Developer—
Utility / transmission ownerDayton

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata