Hoot Lake Solar (65066_1)

Hoot Lake Solar is a 49.9 MW solar interconnection project in Otter Tail, Minnesota with a current status of operational.

49.9 MWCapacity
OperationalStatus
MISOMarket
SolarTechnology

Project facts

Canonical nameHoot Lake Solar
Queue ID65066_1
Statusoperational
Source status(OP) Operating
MarketMISO
TechnologySolar
Capacity49.9 MW
StateMinnesota
CountyOtter Tail
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date2023-08-01
Withdrawn date
Developer
Utility / transmission ownerOtter Tail Power Company

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata