Hope NW - Fulton 115 kV Line is a 120.0 MW solar interconnection project in Hempstead, Arkansas with a current status of withdrawn. It is proposed to connect at Hope NW - Fulton 115 kV Line.
120.0 MWCapacity
WithdrawnStatus
ARMarket
SolarTechnology
Project facts
| Canonical name | Hope NW - Fulton 115 kV Line |
|---|---|
| Queue ID | GEN-2024-214 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | AR |
| Technology | Solar |
| Capacity | 120.0 MW |
| State | Arkansas |
| County | Hempstead |
| Point of interconnection | Hope NW - Fulton 115 kV Line |
| Requested (queue) date | 2025-03-01 |
| Proposed in-service date | 2029-12-31 |
| Operational date | — |
| Withdrawn date | 2025-08-25 |
| Developer | — |
| Utility / transmission owner | AEP |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata