Hubbard Wind II (69010_5111)

Hubbard Wind II is a 304.5 MW wind interconnection project in Hill, Texas with a current status of operational.

304.5 MWCapacity
OperationalStatus
ERCOMarket
WindTechnology

Project facts

Canonical nameHubbard Wind II
Queue ID69010_5111
Statusoperational
Source status(OP) Operating
MarketERCO
TechnologyWind
Capacity304.5 MW
StateTexas
CountyHill
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2026-08-01
Withdrawn date—
Developer—
Utility / transmission ownerHubbard Wind II, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-02operational_date—2026-08-01medium
2026-10-02proposed_online_date2026-09-01—medium
2026-10-02statusactiveoperationalhigh
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.