Huntley to Blue Earth 161kV (J1572)

Huntley to Blue Earth 161kV is a 150.0 MW solar interconnection project in Faribault, Minnesota with a current status of operational. It is proposed to connect at Huntley to Blue Earth 161kV.

150.0 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical nameHuntley to Blue Earth 161kV
Queue IDJ1572
Statusoperational
Source statusDone
Market
TechnologySolar
Capacity150.0 MW
StateMinnesota
CountyFaribault
Point of interconnectionHuntley to Blue Earth 161kV
Requested (queue) date2020-06-23
Proposed in-service date2023-10-15
Operational date2023-10-15
Withdrawn date
Developer
Utility / transmission ownerNORTHERN STATES POWER COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.