Husky Solar is a 50.2 MW solar interconnection project in Windham, Connecticut with a current status of active. It is proposed to connect at The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N..
Project facts
| Canonical name | Husky Solar |
|---|---|
| Queue ID | 1138 |
| Status | active |
| Source status | A |
| Market | CT |
| Technology | Solar |
| Capacity | 50.2 MW |
| State | Connecticut |
| County | Windham |
| Point of interconnection | The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N. |
| Requested (queue) date | 2021-06-03 |
| Proposed in-service date | 2030-05-10 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | active | high |
Explore related data
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata