Iberdrola Renewables Inc (G112)
Iberdrola Renewables Inc is a 200.0 MW wind interconnection project in Klickitat, Oregon with a current status of withdrawn. It is proposed to connect at On Hanford-JohnDay 500 kV Line, ~8 miles SW of Bickleton.
200.0 MWCapacity
WithdrawnStatus
ORMarket
WindTechnology
Project facts
| Canonical name | Iberdrola Renewables Inc |
|---|---|
| Queue ID | G112 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | OR |
| Technology | Wind |
| Capacity | 200.0 MW |
| State | Oregon |
| County | Klickitat |
| Point of interconnection | On Hanford-JohnDay 500 kV Line, ~8 miles SW of Bickleton |
| Requested (queue) date | 2002-11-01 |
| Proposed in-service date | 2004-03-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Avangrid Power, LLC |
| Utility / transmission owner | Bonneville Power Administration |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata