IL Bolingbrook 279 Marquette Dr is a 1.0 MW solar interconnection project in Will, Illinois with a current status of operational.

1.0 MWCapacity
OperationalStatus
PJMMarket
SolarTechnology

Project facts

Canonical nameIL Bolingbrook 279 Marquette Dr
Queue ID68539_19572
Statusoperational
Source status(OP) Operating
MarketPJM
TechnologySolar
Capacity1.0 MW
StateIllinois
CountyWill
Point of interconnection
Requested (queue) date
Proposed in-service date
Operational date2025-05-01
Withdrawn date
Developer
Utility / transmission ownerCatalyze Bolingbrook 279 Marquette Drive Microgrid, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectoperationalhigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata