Independence Power & Light, Blue Valley Substation, 161kV Bus (GEN-2021-042)

Independence Power & Light, Blue Valley Substation, 161kV Bus is a 50.0 MW battery interconnection project in Jackson, Missouri with a current status of active. It is proposed to connect at Independence Power & Light, Blue Valley Substation, 161kV Bus.

50.0 MWCapacity
ActiveStatus
MOMarket
BatteryTechnology

Project facts

Canonical nameIndependence Power & Light, Blue Valley Substation, 161kV Bus
Queue IDGEN-2021-042
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketMO
TechnologyBattery
Capacity50.0 MW
StateMissouri
CountyJackson
Point of interconnectionIndependence Power & Light, Blue Valley Substation, 161kV Bus
Requested (queue) date2021-04-30
Proposed in-service date2028-05-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerINDN

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.