INDN — Interconnection Queue Projects
INDN is associated with 6 tracked interconnection projects representing 553 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
6Projects
4Active
0Operational
2Withdrawn
553 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Battery | 4 | 415 MW |
| Other | 2 | 138 MW |
Geographic footprint
| State | Projects |
|---|---|
| Missouri | 6 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Eckles Road 161 kV Substation | GEN-2023-036 | Battery | 165.0 MW | withdrawn | Jackson, Missouri |
| Sub M 161 kV Substation | GEN-2023-171 | Battery | 150.0 MW | active | Jackson, Missouri |
| Blue Valley Station 69 kV | GEN-2021-GR1 | — | 88.0 MW | withdrawn | Independence, Missouri |
| Blue Valley 161kV Substation | GEN-2025-SR18 | Other | 50.0 MW | active | Indepedence, Missouri |
| Blue Valley 161kV Substation | GEN-2018-031 | Battery | 50.0 MW | active | Jackson, Missouri |
| Independence Power & Light, Blue Valley Substation, 161kV Bus | GEN-2021-042 | Battery | 50.0 MW | active | Jackson, Missouri |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.