Indigo Solar 3 (28INR0067)

Indigo Solar 3 is a 800.0 MW solar interconnection project in Fisher, Texas with a current status of operational. It is proposed to connect at Tap Line Segment Tankawa (Bus #1048) to Graham (Bus #1430) .

800.0 MWCapacity
OperationalStatus
FisherMarket
SolarTechnology

Project facts

Canonical nameIndigo Solar 3
Queue ID28INR0067
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketFisher
TechnologySolar
Capacity800.0 MW
StateTexas
CountyFisher
Point of interconnectionTap Line Segment Tankawa (Bus #1048) to Graham (Bus #1430)
Requested (queue) date2024-10-29
Proposed in-service date
Operational date2028-11-01
Withdrawn date
DeveloperIndigo Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata