Inertia Solar (22INR0374)

Inertia Solar is a 202.4 MW solar interconnection project in Haskell, Texas with a current status of operational. It is proposed to connect at tap 345kV 60515 Clear Crossing - 6104 Smoky Hill.

202.4 MWCapacity
OperationalStatus
HaskellMarket
SolarTechnology

Project facts

Canonical nameInertia Solar
Queue ID22INR0374
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketHaskell
TechnologySolar
Capacity202.4 MW
StateTexas
CountyHaskell
Point of interconnectiontap 345kV 60515 Clear Crossing - 6104 Smoky Hill
Requested (queue) date2021-02-02
Proposed in-service date
Operational date2029-03-31
Withdrawn date
DeveloperInertia Solar Project, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata