Interconnecting at Hugo - Sunnyside 345 kV transmission line (GEN-2024-SR6)

Interconnecting at Hugo - Sunnyside 345 kV transmission line is a 200.0 MW battery interconnection project in Johnston County, Oklahoma with a current status of active. It is proposed to connect at Interconnecting at Hugo - Sunnyside 345 kV transmission line.

200.0 MWCapacity
ActiveStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameInterconnecting at Hugo - Sunnyside 345 kV transmission line
Queue IDGEN-2024-SR6
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketOK
TechnologyBattery
Capacity200.0 MW
StateOklahoma
CountyJohnston County
Point of interconnectionInterconnecting at Hugo - Sunnyside 345 kV transmission line
Requested (queue) date2024-02-20
Proposed in-service date2027-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerOG&E

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata