Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line (GEN-2018-072)
Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line is a 151.0 MW battery interconnection project in Kay, Oklahoma with a current status of active. It is proposed to connect at Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line.
Project facts
| Canonical name | Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line |
|---|---|
| Queue ID | GEN-2018-072 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SCHEDULE |
| Market | OK |
| Technology | Battery |
| Capacity | 151.0 MW |
| State | Oklahoma |
| County | Kay |
| Point of interconnection | Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line |
| Requested (queue) date | 2018-10-26 |
| Proposed in-service date | 2027-12-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | OGE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata