Kay County, Oklahoma — Interconnection Projects
The interXdata warehouse tracks 23 interconnection projects in Kay, Oklahoma, representing 2,993 MW of requested capacity.
23Total projects
4Active
14Operational
5Withdrawn
2,993 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 12 | 1,873 MW |
| Gas | 5 | 359 MW |
| Battery | 3 | 352 MW |
| Solar | 1 | 250 MW |
| Other | 2 | 158 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Frontier Windpower II | 62837_FW2 | Wind | 351.8 MW | operational | Kay, Oklahoma |
| Kay Wind, LLC | 59460_KNG1 | Wind | 299.0 MW | operational | Kay, Oklahoma |
| Rose Hill-(Ranch Road) Sooner (Open Sky) 345kV | GEN-2012-032 | Wind | 299.0 MW | operational | Kay, Oklahoma |
| Ranch Road 345 kV Substation | GEN-2023-211 | Solar | 250.0 MW | withdrawn | Kay, Oklahoma |
| Rose Hill (Open Sky)-Sooner (Ranch Road) 345kV | GEN-2015-001 | Wind | 200.0 MW | operational | Kay, Oklahoma |
| Frontier Windpower | 60218_FC1 | Wind | 200.0 MW | operational | Kay, Oklahoma |
| Rock Falls Wind Farm LLC | 61261_RF1 | Wind | 154.5 MW | operational | Kay, Oklahoma |
| Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line | GEN-2018-072 | Battery | 151.0 MW | active | Kay, Oklahoma |
| Interconnecting into OG&E's Ranch Road 345kV substation by tapping a 0.1 gen tie line into the existing Frontier II gen-tie line | GEN-2018-071 | Battery | 151.0 MW | active | Kay, Oklahoma |
| Hardy 138 kV Substation | GEN-2016-148 | Wind | 150.0 MW | withdrawn | Kay, Oklahoma |
| Charles D. Lamb Energy Center | 58325_1 | Gas | 122.0 MW | operational | Kay, Oklahoma |
| Rose Hill (Open Sky)-Sooner (Ranch Road) 345kV | GEN-2012-041 | Other | 121.5 MW | operational | Kay, Oklahoma |
| Ranch Road 345 kV Substation | GEN-2024-334 | Gas | 103.0 MW | operational | Kay, Oklahoma |
| Chilocco 138kV | GEN-2012-040 | Wind | 76.5 MW | withdrawn | Kay, Oklahoma |
| Middleton Tap 138kV Substation | GEN-2016-071 | Wind | 64.6 MW | active | Kay, Oklahoma |
| Ponca City | 7546_4 | Gas | 60.5 MW | operational | Kay, Oklahoma |
| NextEra-Blackwell Wind, LLC | 58209_WT | Wind | 59.8 MW | operational | Kay, Oklahoma |
| Ponca City | 7546_3 | Gas | 54.0 MW | operational | Kay, Oklahoma |
| Tap Medford Tap – Coyote 138kV | GEN-2024-SR17 | Battery | 50.0 MW | active | Kay, Oklahoma |
| Kaw Hydro | 7545_1 | Other | 37.0 MW | operational | Kay, Oklahoma |
| Ponca City | 7546_1 | Gas | 19.8 MW | operational | Kay, Oklahoma |
| Open Sky 345kV | GEN-2014-022 | Wind | 15.0 MW | withdrawn | Kay, Oklahoma |
| Nardins 69kV | GEN-2015-028 | Wind | 3.0 MW | withdrawn | Kay, Oklahoma |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Kay County.