J1347 TO Switchyard (115kV Entergy MS Switchyard) (J4131)

J1347 TO Switchyard (115kV Entergy MS Switchyard) is a 100.0 MW battery interconnection project in Scott, Mississippi with a current status of operational. It is proposed to connect at J1347 TO Switchyard (115kV Entergy MS Switchyard).

100.0 MWCapacity
OperationalStatus
Market
BatteryTechnology

Project facts

Canonical nameJ1347 TO Switchyard (115kV Entergy MS Switchyard)
Queue IDJ4131
Statusoperational
Source statusActive
Market
TechnologyBattery
Capacity100.0 MW
StateMississippi
CountyScott
Point of interconnectionJ1347 TO Switchyard (115kV Entergy MS Switchyard)
Requested (queue) date2025-10-01
Proposed in-service date2030-06-01
Operational date2030-06-01
Withdrawn date
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.