Jefferson - Hanging Rock 765 kV (AH2-353)

Jefferson - Hanging Rock 765 kV is a 1,000.0 MW solar interconnection project in N/a, Kentucky with a current status of withdrawn.

1,000.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameJefferson - Hanging Rock 765 kV
Queue IDAH2-353
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity1,000.0 MW
StateKentucky
CountyN/a
Point of interconnection—
Requested (queue) date2022-03-10
Proposed in-service date2028-12-31
Operational date—
Withdrawn date2026-04-08
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-11
Data last materially changed2026-10-11
Page data generated2026-10-11

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.