Jerome - Mohicanville 69 kV (AH1-069 - moved to TC2)

Jerome - Mohicanville 69 kV is a 17.0 MW solar interconnection project in Ashland, Ohio with a current status of withdrawn.

17.0 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameJerome - Mohicanville 69 kV
Queue IDAH1-069 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity17.0 MW
StateOhio
CountyAshland
Point of interconnection—
Requested (queue) date2021-07-28
Proposed in-service date2027-11-11
Operational date—
Withdrawn date2025-12-01
Developer—
Utility / transmission ownerATSI

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata