Jonesboro - Independence 161 kV (GEN-2023-132)

Jonesboro - Independence 161 kV is a 150.0 MW solar interconnection project in Craighead, Arkansas with a current status of active. It is proposed to connect at Jonesboro - Independence 161 kV.

150.0 MWCapacity
ActiveStatus
ARMarket
SolarTechnology

Project facts

Canonical nameJonesboro - Independence 161 kV
Queue IDGEN-2023-132
Statusactive
Source statusIA PENDING
MarketAR
TechnologySolar
Capacity150.0 MW
StateArkansas
CountyCraighead
Point of interconnectionJonesboro - Independence 161 kV
Requested (queue) date2023-10-02
Proposed in-service date2028-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerSWPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.