Jourdanton BESS (27INR0433)

Jourdanton BESS is a 9.8 MW battery interconnection project with a current status of withdrawn. It is proposed to connect at Station Name: Jourdanton_x000D_ Station Code: JOURDNTN_x000D_ Load/Load Transformer Name: TR1X _x000D_ PTI BUS number: 8607 _x000D_ Voltage in kV: 69 kV.

9.8 MWCapacity
WithdrawnStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameJourdanton BESS
Queue ID27INR0433
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyBattery
Capacity9.8 MW
State
County
Point of interconnectionStation Name: Jourdanton_x000D_ Station Code: JOURDNTN_x000D_ Load/Load Transformer Name: TR1X _x000D_ PTI BUS number: 8607 _x000D_ Voltage in kV: 69 kV
Requested (queue) date2024-11-07
Proposed in-service date2025-12-31
Operational date
Withdrawn date
DeveloperJourdanton BESS LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata