Junction North BESS (23INR0619)

Junction North BESS is a 9.9 MW battery interconnection project with a current status of operational. It is proposed to connect at Station Name: New Junction _x000D_ Station Code: P_NEWJUNC_1_ _x000D_ PTI Bus#: 70600_x000D_ Load XFMR Name: PEC Load ID: 1 << The planning cases do not have "Load Names" only a two character Load ID _x000D_ Transmission Level Voltage: 69 kV.

9.9 MWCapacity
OperationalStatus
ERCOTMarket
BatteryTechnology

Project facts

Canonical nameJunction North BESS
Queue ID23INR0619
Statusoperational
Source statusoperational
MarketERCOT
TechnologyBattery
Capacity9.9 MW
State
County
Point of interconnectionStation Name: New Junction _x000D_ Station Code: P_NEWJUNC_1_ _x000D_ PTI Bus#: 70600_x000D_ Load XFMR Name: PEC Load ID: 1 << The planning cases do not have "Load Names" only a two character Load ID _x000D_ Transmission Level Voltage: 69 kV
Requested (queue) date2023-06-14
Proposed in-service date2024-11-30
Operational date2025-03-03
Withdrawn date
DeveloperSBESS TX 3, LLC
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.