Katydid Road 345 kV is a 50.0 MW battery interconnection project in Lasalle, Illinois with a current status of active.

50.0 MWCapacity
ActiveStatus
—Market
BatteryTechnology

Project facts

Canonical nameKatydid Road 345 kV
Queue IDAF2-319 - moved to TC1
Statusactive
Source statusEngineering and Procurement
Market—
TechnologyBattery
Capacity50.0 MW
StateIllinois
CountyLasalle
Point of interconnection—
Requested (queue) date2020-03-30
Proposed in-service date2029-03-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerComEd

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.