KCE NY 21 (C24-010)

KCE NY 21 is a 60.0 MW battery interconnection project in Suffolk, New York with a current status of active. It is proposed to connect at Pulaski 69kV Substation.

60.0 MWCapacity
ActiveStatus
KMarket
BatteryTechnology

Project facts

Canonical nameKCE NY 21
Queue IDC24-010
Statusactive
Source status7
MarketK
TechnologyBattery
Capacity60.0 MW
StateNew York
CountySuffolk
Point of interconnectionPulaski 69kV Substation
Requested (queue) date2024-08-01
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperKCE NY 21, LLC
Utility / transmission ownerLIPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata