KCE NY 30 (1448)

KCE NY 30 is a 50.0 MW battery interconnection project in Suffolk, New York with a current status of withdrawn. It is proposed to connect at West Babylon 69kV substation.

50.0 MWCapacity
WithdrawnStatus
KMarket
BatteryTechnology

Project facts

Canonical nameKCE NY 30
Queue ID1448
Statuswithdrawn
Source status0
MarketK
TechnologyBattery
Capacity50.0 MW
StateNew York
CountySuffolk
Point of interconnectionWest Babylon 69kV substation
Requested (queue) date2022-10-11
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperKCE NY 30, LLC
Utility / transmission ownerLIPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.