Kendall 345kV (AB2-154)

Kendall 345kV is a 65.0 MW gas interconnection project in Kendall, Illinois with a current status of withdrawn.

65.0 MWCapacity
WithdrawnStatus
—Market
GasTechnology

Project facts

Canonical nameKendall 345kV
Queue IDAB2-154
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyGas
Capacity65.0 MW
StateIllinois
CountyKendall
Point of interconnection—
Requested (queue) date2016-04-29
Proposed in-service date2017-05-01
Operational date—
Withdrawn date2016-09-27
Developer—
Utility / transmission ownerComEd

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata