Key City Battery Storage SLF (26INR0700)

Key City Battery Storage SLF is a 1.9 MW other interconnection project in Taylor, Texas with a current status of operational. It is proposed to connect at 6235 Abilene Mulberry Creek 345.

1.9 MWCapacity
OperationalStatus
TaylorMarket
OtherTechnology

Project facts

Canonical nameKey City Battery Storage SLF
Queue ID26INR0700
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketTaylor
TechnologyOther
Capacity1.9 MW
StateTexas
CountyTaylor
Point of interconnection6235 Abilene Mulberry Creek 345
Requested (queue) date2025-07-07
Proposed in-service date
Operational date2029-03-31
Withdrawn date
DeveloperKey City Battery Storage LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.