Keystone-Desoto 345 kV (AF1-119)

Keystone-Desoto 345 kV is a 200.0 MW solar interconnection project in Blackford, Indiana with a current status of active.

200.0 MWCapacity
ActiveStatus
Market
SolarTechnology

Project facts

Canonical nameKeystone-Desoto 345 kV
Queue IDAF1-119
Statusactive
Source statusEngineering and Procurement
Market
TechnologySolar
Capacity200.0 MW
StateIndiana
CountyBlackford
Point of interconnection
Requested (queue) date2019-09-13
Proposed in-service date2028-01-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.