Kickstart Energy Storage I (27INR0469)

Kickstart Energy Storage I is a 1.4 MW other interconnection project in Ellis, Texas with a current status of operational. It is proposed to connect at Tap 345 kV 1907 Venus Switch - 3383 BYNUM_5.

1.4 MWCapacity
OperationalStatus
EllisMarket
OtherTechnology

Project facts

Canonical nameKickstart Energy Storage I
Queue ID27INR0469
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEllis
TechnologyOther
Capacity1.4 MW
StateTexas
CountyEllis
Point of interconnectionTap 345 kV 1907 Venus Switch - 3383 BYNUM_5
Requested (queue) date2025-03-24
Proposed in-service date
Operational date2029-09-30
Withdrawn date
DeveloperKickstart Infrastructure LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.