Kiowa Substation 115kV (90753) (GEN-2018-075)

Kiowa Substation 115kV (90753) is a 230.0 MW other interconnection project in Eddy, New Mexico with a current status of withdrawn. It is proposed to connect at Kiowa Substation 115kV (90753).

230.0 MWCapacity
WithdrawnStatus
NMMarket
OtherTechnology

Project facts

Canonical nameKiowa Substation 115kV (90753)
Queue IDGEN-2018-075
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologyOther
Capacity230.0 MW
StateNew Mexico
CountyEddy
Point of interconnectionKiowa Substation 115kV (90753)
Requested (queue) date2018-10-26
Proposed in-service date
Operational date
Withdrawn date2019-04-16
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.